The HREL Norfolk Segment 1A will repurpose I-64 in both directions from Tidewater Drive to Patrol Road in Norfolk. The three existing general purpose lanes and shoulders will be converted to one part-time, high-occupancy shoulder Express Lane and three general purpose lanes for a total of 2 miles.
This project is currently under construction. The HREL Norfolk Segment 1B is in design.
Project Awarded: Fall 2022
Estimated Project Completion: Early 2026
Design-Build Contract Cost: $163 Million
Estimated Overall Project Cost: $197.6 Million
Contractor: Design-Build, Allan Myers
Major Work Items:
Fall 2023 Construction Outlook:
Project Updates:
Sign up to receive Project news and traffic alerts for this area in the city of Norfolk.
Traffic Alerts/News Releases:
511 Traffic camera views in this area include, but are not limited to:
Project Documents:
The Citizen Information Meeting for the Hampton Roads Express Lanes Norfolk Segment 1A was held on Aug. 22, 2023. Project boards shown at the meeting are included below.
Citizens should direct questions and comments to HRELNorfolk@AllanMyers.com or 757-250-3045. Media should direct questions to HamptonRoadsPublicInfo@VDOT.Virginia.gov or 757-956-3032.
Meeting Materials: