The HREL Norfolk Segment will repurpose I-64 in both directions from I-264 in Virginia Beach to I-564 in Norfolk. The three existing general purpose (GP) lanes and shoulders will be converted to one part-time, high-occupancy express shoulder lane and three GP lanes. The bridges over Tidewater Drive will be widened and rehabilitated. Several existing bridges along the corridor will be rehabilitated and spot widening will occur to accommodate the typical section along the corridor.

Major Work Items:
  • Noise walls
  • Four bridge replacements (EB/WB Tidewater Drive, EB/WB Chesapeake Boulevard)
  • Nine miles of shoulder rehabilitation/strengthening in each direction
  • Roadway widening in spot locations to maintain minimum shoulder width
  • Right of way acquisition in spot locations
  • Tolling gantries
  • Overhead signage
Project Cost: $192 Million
Important Dates
  • Request For Qualifications: Fall 2021
  • Virtual Public Hearing Dec. 1 at 5:30 p.m.
    Click here to register via WebEx
  • In-person Public Hearing Dec. 2, 4-7 p.m. at the
    Residence Inn Norfolk Airport, 1590 N. Military Highway, Norfolk, VA 23502
  • Request for Proposals: Winter 2022
  • Notice to Proceed: Summer 2022
  • Fixed Completion Date: Winter 2025

Click here to register for the Virtual Public Hearing Dec. 1 at 5:30 p.m. via WebEx 

In-person public hearing Dec. 2, 4-7 p.m. at the  
Residence Inn Norfolk Airport
1590 N. Military Highway, Norfolk, VA 23502

 Click here for Public Hearing Information and Project Boards