The HREL Hampton Segment includes converting the three existing eastbound and westbound GP lanes into two Express Lanes and two GP lanes. The project will widen I-64 and re-pave existing lanes with an additional 12-foot-wide travel lane in each direction from east of Settlers Landing Road (exit 267) to LaSalle Avenue (exit 265). This section of interstate includes six mainline bridges and one pedestrian underpass. The eastbound Hampton River bridges will be replaced, and the westbound Hampton River Bridge will be widened and rehabilitated.
Project Awarded: Summer 2022
Project Completion: Late 2026
Design-Build Contract: $313.9 Million
Contractor: Design-Build, Shirley-Branch Joint Venture
Spring 2023 Construction Outlook:
Project Documents:
Public Hearing Information and Project Boards
Categorical Exclusion Approval
Current Sequence of Construction
All work is dependent on weather conditions and the schedule is subject to change.
511 Traffic camera views in this area include, but are not limited to: